PROJECT APPLICATION AND REFFERENCES

NNEG STEAM PIPELINE AND 115KV & 22 KV TRANSMISSION LINES PROJECT (Site TOSTEM-2 (NORTH)​

PROJECT DATA

LOCATION​NNEG STEAM PIPELINE AND 115KV & 22 KV TRANSMISSION LINES PROJECT (Site TOSTEM-2 (NORTH)​
OWNERNAVA NAKORN ELECTRICITY GENERATING CO., LTD. (NNEG)
MAINCONTRACTOR​THAI SHINRYO LIMITED
YEAR OFCOMPLETION​YEAR 2015
CONTRACTVALUE​

PROJECT DESCRIPTION​

PIPELINE DISTRIBUTION AND OTHER WORK​

  • ENGINEERING AND DOCUMENT WORK​
  • FLOW METER AND ACCESSORIES METERING STATION​
  • FLOW COMPUTER AND CONTROL SYSTEM​

TECHTRONIC SCOPE OF WORK 

BASIC DESIGN​DETAIL ENGINEERING
CONSTRUCTION SUPERVISION &COMMISSIONING​STARTUP​

CONDITION DATA : MEDIUM PRESSURE STEAM 

FLOW (TON/HR)8.4
PRESSURE (Kg/Cm2)6(+/-1)
TEMPERATURE (°C)165(+/-5)
PIPE SIZE (INCH)6
DISTRIBUTION LENGTH (M) ​