PROJECT DATA
| PROJECT NAME | OPPORTUNITY IMPORT HN TO REFINARY PROJECT |
| OWNER | PTT GLOBAL CHEMICAL PUBLIC COMPANY LIMITED |
| MAINCONTRACTOR | PTT GLOBAL CHEMICAL PUBLIC COMPANY LIMITED |
| YEAR OFCOMPLETION | YEAR 2024 |
| CONTRACTVALUE |
PROJECT DESCRIPTION
PIPELINE DISTRIBUTION AND OTHER WORK
- ENGINEERING AND DOCUMENT WORK
- FLOW METER AND ACCESSORIES METERING STATION
- FLOW COMPUTER AND CONTROL SYSTEM
- MANUAL VALVE AND ACCESSORIES
TECHTRONIC SCOPE OF WORK
| BASIC DESIGN | DETAIL ENGINEERING |
| PROJECT MANAGEMENT | PROCUREMENT |
| FABRICATION AND INSTALLATION | COMMISSIONING AND STARTUP |
CONDITION DATA : : CUSTODY CRUDE METERING SKID
| FLOW (TON/HR) | 150 |
| PRESSURE (Kg/Cm2) | 3.5 |
| TEMPERATURE (°C) | AMBIEN |
| PIPE SIZE (INCH) | 6 |
| METER TYPE | HEAVY NAPHTHA |